Cardinal Change and Payment
"A contractor faced with a substantial change in its originally contracted scope of work, who is unable to successfully negotiate a price for that additional work, may elect to continue to work and reserve its right to subsequently obtain a judicial determination as to the value of the changes, so long as the other contracting party continues to demand performance of the increased scope of work, and in the absence of any conflicting provision of the contract." Ted Jacob Engineering Group v. Ratcliff Architects , 2010 WL 3294341 (Cal.App. 1 Dist.). Trenton H. Cotney Florida Bar Certified in Construction Law Glenn Rasmussen Fogarty & Hooker, P.A. 100 S. Ashley Dr., Suite 1300 Tampa, FL 33602 (813) 229-3333 www.trentcotney.com