Force Majeure Clause and Two Year ILSA Completion Exemption

In Stein v. Paradigm Mirasol , LLC, 2009 WL 3110819 (11th Cir. 2009), the Court held that a force majeure clause (a/k/a Acts of God clause) did not nullify the use of the two-year completion exemption in the Interstate Land Sales Act (ILSA).   Trenton H. Cotney Board Certified in Construction Law Trent Cotney, P.A. 1207 N Franklin St, Ste 222 Tampa, FL 33602 (813) 579-3278 www.trentcotney.com

Recent Case: ILSA Exemption

In Pohlman v. Aqua Condominium Developers , 44 So.3d 645 (Fla. 1st DCA 2010) which followed Aikin v. WCI Communities , 26 So. 3d 691 (Fla. 2d DCA 2010), but conflicted with Plaza Court v. Baker-Chaput , 17 So. 3d 720 (Fla. 5th DCA 2009), the Court affirmed the dismissal of the contract purchasers’ action seeking rescission based on the developer’s failure to comply with the ILSA exemption regarding the seller’s obligation to complete construction within 2 years where such obligation is excused under applicable Florida contract law.  A contract provisions allowing for additional time in the event of construction delays did not make the obligation to complete construction in two years illusory. Trenton H. Cotney Florida Bar Certified in Construction Law Glenn Rasmussen Fogarty & Hooker, P.A. 100 S. Ashley Dr., Suite 1300 Tampa, FL 33602 (813) 229-3333 http://www.glennrasmussen.com