When general contractors or subcontractors sign on to construction projects, they usually start off believing everything will run smoothly. But, during the course of the work, issues sometimes arise that force all parties to go running back to their contracts in order to evaluate their options. One of those options for construction companies is to simply stop work, but contractors need to take care when making such a big decision. “Stopping work and ultimately terminating the contract is one of the most radical things you can do,” said Joseph McManus Jr., attorney and shareholder at law firm Carlton Fields. Luckily, most of the circumstances under which contractors are clearly entitled to stop work are included in the most popular standard forms of contracts. Nonpayment The most common reason that contractors find it necessary to stop work, McManus said, is that they haven’t been paid for approved invoices. In that scenario, he said, contractors have the right to