Differing Site Conditions Clauses: Part V
Under the Hendry decision mentioned in Part IV,
the contractor was not able to recover an equitable adjustment to the contract
price when the contractor discovered that the bridge pilings to be removed were
wood, rather than concrete as anticipated.
The contractor was denied additional compensation despite the fact that
the owner had in its possession plans from when the original pilings were
installed showing that the piles were wood. The contractor argued that the owner had
misrepresented the true site conditions by failing to disclose all of the
information to the bidders. There are
additional facts unique to the Hendry case that help explain why the
court denied any recovery, but the case can still be cited for the proposition
that a public owner in Florida does not have the duty to disclose superior
knowledge regarding site conditions as long as the owner has not misrepresented
the conditions to be encountered.
Trenton H. Cotney
Board Certified in Construction Law
Board Certified in Construction Law
Trent Cotney, P.A.
1207 N Franklin St, Ste 222
Tampa, FL 33602
(813) 579-3278
Such an nice post
ReplyDelete"All Stars Roofing is a Roofing company Offering Roof Repair and Roofing installation services in Oakville, Burlington, Mississauga, Etobicoke, Halton Hills."
Hamilton Roofing
Roof Repair Mississauga
Roofing Companies Oakville
Roofing Oakville
Roofing Burlington
http://allstarsroofing.com/