Delay Damages and Payment Bond Claims

In Fisk Electric Co. v. Travelers Casualty and Surety Co., 2009 WL 196032 (S.D. Fla. 2009), the Court held that a subcontractor could pursue delay damages against a surety based on a private payment bond.  The Court reasoned that the language of the private bond was simliar to a Miller Act bond and that language would allow the subcontractor to pursue delay damges.